Power steel pole installation process
Foundation excavation: Excavate the foundation as required, and then pour concrete.
Manufacturing and assembly: The pre-fabricated components are transported to the site for assembly, including the pole body, cross arm, hanging point and other parts.
Transportation and installation: After the assembly is completed, the power steel lattice pole is hoisted with lifting equipment and placed in the pre-laid foundation hole, and then the surrounding gap is filled with gravel, cement and other materials to fix the power steel pole on the foundation. Dynamic balance: For large power steel poles, dynamic balance tests are required.
Grounding: The power steel pole needs to be grounded to the ground to reduce the risk of fire and lightning strikes.
Wire installation: The transmission wire is fixed to the installed power steel pole and then connected to the power grid of the power station or substation.